Please be aware that VDOT will be performing routine maintenance on Avon Drive this week in addition to the streets mentioned below. As of now, the following streets will also be serviced in the following weeks
-Candlestick Ct. (10/31-Milling, 11/2-Paving )
-Beaver Dam Rd. (11/1-Milling, 11/3-Paving)
-Cliffbrook Ct. (11/1-Milling, 11/3-Paving)
-Spillway Ln. (11/2-Milling, 11/4-Paving)
-Dolphin Dr. (11/3-Milling, 11/6-Paving)
-Fairway Dr. (11/4-Milling, 11/8-Paving)
-Ashgrove Dr. (11/6-Milling, 11/7-Paving)
If you have any questions or concerns, please reach out to VDOT at (703) 383-8368.