Community News 1/28/2020

Montclair Community News – January 28, 2020 Coffee with the Candidates Saturday, February 15, 2020 at 10 a.m. MPOA Office Go beyond seeing names on a ballot – here’s your chance to get to know the 2020 MPOA Board of Director candidates over a cup of coffee. Candidates will present their goals and ideas for the community and answer questions. Put a face to a name, get to know your neighbors and enjoy a cup of coffee on us. Can't make it to the meeting? Recording access documents can also be found on FSR Connect at https://montclairva.connectresident.com/ under “Association Documents” > “Recordings.” Having trouble finding documents on FSR Connect? When you log into your account, you’re taken

Community News 1/14/2020

Montclair Community News – January 14, 2020 Lake Montclair Lowering Lake Montclair will be lowered by as much as 3 ft. starting on Friday, January 17, 2020 to safely install the back-up sluice gate. The installation is expected to take four days, with a target completion date of Friday, January 24, 2020. Lakefront property owners are encouraged to take any necessary actions to protect their property while these repairs take place. This includes, but is not limited to, adjusting pontoon retaining lines and properly securing or removing boats, canoes or kayaks. After the required work is completed, the sluice gates will be closed and the water will naturally return to its regular level. Precip

Lake Montclair Lowering Rescheduled

Due to forecasted precipitation this week and short notification received from the contractor, the installation of the back-up sluice gate has been postponed until Tuesday, January 21, 2020 (weather permitting). Therefore, the lake lowering process has been halted and the level will not be additionally lowered as previously announced. For those who may not be aware, the work commencing on January 21st is for the installation of a backup sluice gate. This project was approved by the Board of Directors at the September 2019 meeting. However, a delay in the receipt of necessary parts prevented the job from moving forward during the December lowering of the lake.

Lake Montclair Lowering Notice

On Monday, January 6, 2020, the water level of Lake Montclair will be lowered by no more than 3 ft. for continued repairs to the back-up sluice gate on the dam. The repairs are schedule to begin on January 7, 2020 pending any delays or weather constraints. Lakefront property owners are encouraged to take any necessary actions to protect their property while these repairs take place. This includes, but is not limited to, adjusting pontoon retaining lines and properly securing or removing boats, canoes or kayaks. The repairs are expected to take four days. After the required work is completed, the sluice gates will be closed and the water will naturally return to its regular level. Precipitati

Recent Posts
Search By Tags
Archive

© 2019 Montclair Property Owners Association